国外项目分包合同样本(中英对照)

欢迎共阅

分包合同协议

SUBCONTRACT AGREEMENT

该合同签订于2014年__月__日,签订地址:____________

THIS AGREEMENT is made the ______ day of _______2014,at_______________

合同双方

BETWEEN

甲方:是在___法律下单独构成、成立的一个公司,其公司总部在:________________在(国家)

注册的办公室在:地址(以下称为“承包商”)

M/s Xinjiang Beixin Road & Bridge Group Co., Ltd a company duly organized and existing under

terms and Conditions as described in the Main Contract unless otherwise stated in this

Subcontract Agreement (hereinafter referred to as the "Subcontract Agreement or

Subcontract") to the Subcontractor and

3. 同时分包商已经同意作为分包商执行该工程,并同意完成分包工程的施工及维修,其分包工

程在承包商的指示及监督下实施,并严格按照分包商合同规定的条款执行及业主与承包商签

订的主合同条款实施工程。

3. While the Subcontractor has agreed to execute the said works as Subcontractor, and to

complete and maintain the proposed part of the Subcontract Work herein agreed, under

the direction and supervision of the Contractor and strictly in accordance with the

provisions stipulated in the Subcontract as well as Main Contract signed in between the

Contractor and the Employer.

4. 构成合同的文件应认为是互相说明的。为了解释的目的,文件的优先次序如下:

4. The documents forming the Subcontract are to be taken as mutually explanatory of one

another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence:

a) 分包协议

a) The Sub Contract Agreement

b) 中标函

b) Letter of Acceptance

c) 备忘录(如果有)

c) Memorandum of Understanding (if any)

d) 分包合同特殊条款

d)

e)

e)

f)

f) General

g)

g)

h)

h)

5.

6.

包商支付。

6. The

execution and completion of the Works and the remedying of defects therein, the Contract Price at the times and in the manner prescribed by the Contract.

此立据。本协议书于上面所定的日期,由合同双方根据各自的法律签署订立,开始执行。

IN WITNESS WHEREOF the parties hereto have caused this Agreement to be executed

中标通知书

Letter of Acceptance

致:中标单位(分包商)日期:

To: XXX (name of Subcontractor) Date:

关于实施____项目分包工程_________中标通知书

为:____________

This is to

中标金额10%

Security as per the

特别提醒:

弃履约本分包工程,

receive this LOA,

hereby shall become void.

新疆北新路桥集团股份有限公司

Xinjiang Beixin Road & Bridge Group Co., Ltd

第D部分-分包合同特殊条款

Section D-Particular Conditions of Subcontract Agreement

以下特殊合同条款(PC)将作为通用合同条款(GC)修正和补充。当通用条款与特殊条款出现分歧时,应以特殊条款为准。

The followings Particular Conditions and clauses (PC) are set forwarding to form as amendment and supplement of the General Conditions (GC) of the Subcontract Agreement. Any disputes arise between the General Conditions and the Particular Conditions of this Subcontract Agreement then the Particular Conditions shall be prevailed.

第E部分-分包合同一般条款

Section E-General Conditions of Subcontract Agreement

Section E

General Condition of Subcontract Agreement

Contents

1. Definition and Explanation

1.1 the “Contractor”

1.2 the “

1.3 the “

1.4 the “

1.5 the “

1.6 the “

1.7 the “

1.8 the “

1.9 the “

1.10 the “

2.

3.4 Reasonable Extension of Time for Completion

3.5 Delayed by Subcontractor

4. General Provisions

4.1 Binding of the Main Contract

4.2 Subcontractor’s Site Inspection

4.3 Subcontractor’s Indemnify

4.4 Subletting of the Subcontract Works

第E部分

分包合同一般条款目录

1.定义和解释

1.1 “承包商”

3.3 施工计划

3.4合理的延期

3.5分包商的延误

4. 一般条款

4.1 主合同的约束力

4.2 分包商的现场考察

4.3 分包商的赔偿

4.5 Setting Out

4.6 Execution of the Temporary Works

5. The Contractor

5.1 Contractor’s Right of Access

5.2 Contractor’s Site Supervision

5.3 Right of the Contractor

5.3.1 Right of Inspection

6.1 Subcontractor

6.2 Subcontractor’

8.Subcontract Price

8.2 Taxes

9. Subcontract Price and Payment

9.1 Mobilization Advance

9.2 Material Advance

9.3 Adjustment in Escalation of Cost

9.4 Application of Interim Payment Certificates

9.5 Final Bill

4.4 分包工程的转包4.5 放样

4.6 临时工程的执行

5. 承包商

5.1 承包商的进入权5.2 承包商的现场监督5.3 承包商的权利

8.2税金

9. 支付

9.1 动员预付款

9.2材料预付款

9.3调差

9.4中期账单

9.5最终账单

9.5.1 Preparation and Submission of the Final Bill

9.5.2 Payment of Final Bill

10.Retention Money

10.1 Deduction of the Retention Money

10.2 Refund of Retention Money

11. Contractor’s Default

11.1 Delay Payment

12. Subcontractor’

12.2 Subcontractor’

15. Variation

17.1 Supply of Material

17.2 Contractor Instructs to Removal

17.3 Inspection from the Employer/Engineer/Contractor 17.4 Contractor’s Control

17.5 Increasing of Insufficient Resource

17.6 Property in Materials and Plant

18. Staff and Labour 10.质保金

10.1质保金的扣除

10.2质保金的返还

11. 承包商的违约

11.1延期支付

11.2主合同终止

17.1 材料的供应

17.2 承包商指示移除的权利17.3业主/工程师/承包商的检查17.4 承包商的控制

17.5 增加不充足的资源

17.6 材料和设备财产

18. 人员及劳工

19. Insurance

19.1 Insurance of Machinery/Equipment and Personnel of the Subcontractor

19.2 Insurance for Subcontractor’s All Risk and Third Party Liability

20. Safety Construction and Environment Protection Policy

21. Handing/Taking Over of the Subcontract Works

21.5 Defects

Certificate

22. Specific Risks

25. Amendments

27. Confidentiality

1.

have the meanings hereby assigned to them,

except where the context otherwise required:

1.1“Contractor" means M/s Xinjiang Beixin Road &

Bridge Group Co., Ltd(which as defined in the Subcontract Data)as contractor in the Main Contract accepted by the Employer& named as “Contractor”in the Subcontract Agreement and includes its authorized representatives, legal successors and any assignees.

1.2 “The Subcontractor” means the party which has signed this Subcontract Agreement with the Contractor 19. 保险

19.1 分包商机械/设备及人员的保险

19.2 分包商的第三方责任险

20. 安全文明施工及实施环境保护方案

21. 分包工程的移交/接管

21.1 完工实验

合同中由业主接受的承包商及本分包

协议下命名的承包商,其包括授权代

表、合法继承人及任何受让人。

1.2“分包商”系指与承包商签订执行本分包协议执行该分包工程的一方,包括其授权代表、法定继承人,但是不包括任何受让人。

1.3“业主”系指在分包合同数据中称为

业主的当事人,及其财产所有权的合法继

承人。

1.4 “工程师”系指由雇主任命并在分包

合同数据中指名,为实施合同担任工程师

for the execution of the Subcontract Works and includes its authorized representatives, legal successors, but not any assignees.

1.3 “Employer" means the person named as employer in the Subcontract Data and the legal successors in title to this person.

1.4“Engineer" means the person appointed by the Employer to act as the Engineer for the purposes of the Contract and named in the Subcontract Data, or other person appointed from time to time by the Employer

1.5 “Main C ontract”

documents,

issued for

Contract.

1.6

in Clause 2 of

1.7 “Subcontract

Agreement signed

Subcontractor,

1.8 “Subcontract

and also subject

deduction

1.9 “Drawings”

employer and detailed construction/shop drawings & As-Built Drawings provided by subcontractor and approved by the Engineer, and covers all drawings, calculation, samples, patterns, models, operation and maintenance manuals or other technical information of similar nature.

1.10 “Specification” means Specifications mentioned in the Main Contract and any specification provided by the Engineer or Contractor to be applied for this Subcontract Works.

2. Scope, Content and Manner of Execution of 的人员,或随时由雇主任命并通知承包商

的其他人员。

1.5 “主合同”指承包商与业主签订的合同,其包括合同文件、规范及颁发的任何组成主合同的补充文件。

1.6“分包工程”是指本分包协议第2条中描述的工作,包括分包商执行的所有工作及完工后及在缺陷期的维修工作。

1.7 “分包合同”指承包商与分包商签订的

的任何措施包括完成永久性工程的辅

助工程、临时工程及建筑、安保的提供

等按照主合同规定的工作,以及工程师

或承包商今后为圆满完成该分包工程

指定的其他工程。

2.3 工程实施

分包合同下所有工程的实施都应按照规

范规定执行,如果规范未提及的,则应

该按照承包商和/或工程师的认可的方式

实施,所有现场的分包工程都应按照工

Subcontract Works

2.1 Scope of the Subcontract Works

The Scope of the Subcontract Works shall be as specified in the Letter of Acceptance or section/scope designated by the Contractor.

2.2 The Content of the Subcontract Works

The contents of the Subcontract Works are as listed in bill of quantities of this Subcontract Agreement and any measures including any works for incorporate in the permanent works as any auxiliary

in the Main

hereafter may

Contractor for

Works.

All work to

the

accordance with

3.

Within 14

the

subcontract

practicable

shall then proceed with the subcontract works with due expedition and reasonable arrangement as planned in the provided Working Schedule and without delay.

3.2 Time for Completion

The Time for Completion of the Subcontract Works is specified in the Subcontract Data which in accordance with the scope of the subcontract works (as limited as clause 2) upon mutual consent of the Contractor and the Subcontractor, and the Subcontractor shall complete the Whole of

程师下达给承包商的合理指示进行实施。

3分包工程的开工、进度计划和延期

3.1分包工程的开工时间

在收到承包商签发的开工指示14天

内或其他书面通知的期限,分包商应

该在开工日期后合理可能的情况下尽

快开始工程的实施,随后应以正当的

在分包工程执行过程中,如果分包商

的施工进度计划落后于原计划的

15%,则承包商将要求分包商在保证

工期不顺延的情况下对原施工计划进

行更新,在更新的进度计划中需要增

加相应的机械、人员等资源以弥补落

后的施工进度计划。分包商在施工过

程中有2次更新施工进度的机会以确

Subcontract Works to reach the satisfaction and approval of the Contractor and/or Engineer.

3.3 Working Program

3.3.1 Submission of Working Program

The Subcontractor shall submit a detailed working program to the Contractor within 15 days after signing of this Subcontract Agreement for approval of the Contractor to be formed as part of the Subcontract Agreement; and the Subcontractor must strictly follow the approved Working Program to execute the works. The Subcontractor is deemed to

climate,

effects

subcontractor’

the

the original

condition that

Completion,

quantity of

recover the

Working

Subcontractor

progress of

matching to

extension of the Time for Completion if the construction progress is delayed by any of the following causes:

(a) A variation of increasing quantity- during

implement of the subcontract works if the increased quantity of key activities is accepted and considered by the Contractor or Engineer for time extension.

(b) By the reason of unforeseeable or force majeure

that seriously affect the planned working

program.

保按期完工。如施工进度仍不能满足

最后一次更新的计划则按照第3.5条

执行。

3.4合理的延期

如果施工进度由于以下任何一种原因造成延迟,则分包商应有权得到工期的延期:

(a) 工程量增加的变更-在施工过程

进行调减或分包范围进行调整。

3.5.2 分包商的工程进度持续落后并没有可靠的保证措施提高施工进度,承包商将考虑按照第13条进行分包合同终止。

3.5.3延期的处罚

(a)如果分包商不能按照分包合同第3条规定的时间内及时完工,则分包商应向承包商

(c) By any circumstances or occurrence (other

than a breach of this Subcontract by the Subcontractor), entitling the Contractor to an extension of his time for completion of the Main Works under the Main Contract; or

(d) Other circumstances duly accepted by the

Contractor that have an influence to the planned

working program.

In any such events as this clause then the Subcontractor can submit application for extension of Time for Completion, the Contractor will make valuation

Time for

basic of claim by

payment.

Clause 3.4 and

of the latest

Contractor will

Subcontract

subcontract works;

3.5.2 If the

but without any

delayed working

take consideration

(a) if the

Liquidated Damages for such default as an amount computed at the rate of 0.1% of the Subcontract Price for each calendar day of delay which shall elapse between the relevant Subcontractor's Time for Completion and the date the Subcontract Works or the relevant section is actually complete, subject to the applicable limit on liquidated damages of 10% of the Subcontract Price. The Contractor may, without prejudice to any method of recovery, deduct such damages, from moneys otherwise becoming due to the Subcontractor. The payment or deduction of such damages shall not, relieve the Subcontractor from his 支付违约赔偿;每延误一天,分包商需支付给承包商分包价格的0.1%的金额,上限为分包价格的10%。延迟的天数,为实际完成分包工程的天数与分包商应完工时间之间的差值。承包商可以,在不影响任何其他扣除方法的情况下,从应该支付给分包商或者将要支付给分包商的款项中将此违约金

分包商有同样的约束力。

4.2分包商的现场考察

分包商被视为在签订合同前他已视察现场及周围环境并充分考虑现场的整体条件和气候条件并表示满意,这些条件包括但不限于地质条件、水文条件、气候条件、征地拆迁、当地民俗、法规、安全、进场通道等情况,并考虑工作的内容及性质、完成工程的

obligations to complete the Subcontract Works or from any other of his obligations and liabilities under the Subcontract.

(b)If before the Subcontractor's Time for Completion of the whole of the Subcontract Works any part has been completed and taken over by the Contractor, the liquidated damages for the delay in completion of the remainder of the Subcontract Works shall be reduced in the proportion which the value of the part so completed and taken over by the Contractor bears to the value of the whole of the Subcontract Works. The provisions of

4

Except

Subcontract

4.2 Subcontractor’

The

inspected and

surroundings

so far as is

Agreement, as

including but

conditions, the

Land

etc. extent

accommodation he may require and, in general the Subcontractor is deem to have taken all the same into account in the Subcontract Price to form the fixed unit price. No additional payment shall be made to Subcontractor separately as a consequence of any expenses incurred to the Subcontractor on account of such conditions as mentioned in this clause.

4.3 Subcontractor’s Indemnify

The Subcontractor shall indemnify and hold harmless the Contractor and its employees against 必要材料以及其可能要求的住宿等,总之分包商被视为已经将这些情况考虑到分包价格中形成固定单价。由于本条款描述的情况对分包商产生的任何费用,将不会给分包商进行另行支付。

4.3分包商的保障

分包商应保护承包商和其雇员免受任

4.6 临时工程的执行

分包商应该执行实施分包工程所需要的所有临时工程如便道、便桥、分包商的临设、现场办公室、实验室等为完成永久工程的设施及必要的辅助工作,分包商要将这些临时工程的信息提供给承包商,对此类临时工程所发生的费用由分包商自行承担,承包商将不另行支

for all losses, damages or claims, expenses, costs, causes of action, liabilities of any nature whatsoever arising out of or in connection with the Subcontract Works.

4.4 Subletting of the Subcontract Works

The Subcontractor shall not assign/sublet the whole or any part of the Subcontract Works (as referred in Clause 2) to any third party without prior written consent of the Contractor. Nevertheless, such consent of the Contractor shall not relive the Subcontractor

4.5 Setting Out

of reference

the correct

positions,

Subcontract

maintain all

marks of the

The

Works as

Subcontractor’s

and etc. any

permanent

be required.

information to the Contractor of these temporary works. All related cost and expense referred to such temporary works shall be duly borne to the Subcontractor to bear by himself and the Contractor shall not make any separately payment accordingly.

5 The “Contractor”

5.1 Right of Access

At any time the Contractor and his employee can access to the site and locations of the Subcontractor as construction site, temporary buildings, storage, offices, workshop and etc. areas

付。

5承包商

5.1进入权

承包商及其雇员可以在任何时候为了工程的监督及其他目的可以随时进入分包商的施工现场、临设、仓库、办公室、设备车间等地方,分包商不得因任

料、设备有缺陷,或与分包合同规范

不符,则承包商可以拒绝这些材料、

设备,并立即通知分包商。分包商应

尽快进行修正、替换,保证被拒绝的

材料、设备能满足分包合同的要求。

承包商执行此类检查、测试的所有费

用以及重复检查、测试的费用应由分

for inspection and other purpose, the Subcontractor shall not by any reason or excuse to interfere Contractor’s access to these site.

5.2 Contractor’s Site Supervision

Accordance to his own arrangement the Contractor may appoint any site inspector for supervision of Subcontractor’s site performance, and hereto the Subcontractor must obey the instruction and orders may be issued by the Site inspector from time to time, whenever the site inspector considered that the executed

satisfied and

activities and

correction of

satisfaction of

Contractor’s

The

and test the

under the

determines

Subcontract

and shall

Plant comply with the Subcontract. All expenses incurred by the Contractor in carrying out such inspections, tests and repetition of such tests and inspections shall be borne by the Subcontractor and shall be deducted from any moneys due to the Subcontractor.

5.3.2 I ncreasing and Reducing

At any time the contractor holds the right to make adjustment of the quantity of the Subcontract Works as increasing, decreasing or divided which in accordance with the site progress of the Subcontractor or due to other necessary reasons.

包商承担,并从分包商应付款里扣除。

5.3.2 增减

承包商任何时候可根据分包商的现场进

度情况或必要的其他原因对分包工程量

进行增减、分割调整的权利。

5.3.3 承包商扣款的权利

承包商有权从分包商的应付款中扣除

同意后方可离场。

6.2 分包商的配合

分包商应与承包商雇佣来实施主合同的其它分包商相互合作。分包商不得由于承包商安排的各分包商之间缺少协作而提出工期延期及发生的任何额外费用的索赔。若由于分包商的失误造成其他分包商及承包商工程延误,那么此类延迟的费用将全部由分包

5.3.3 Right of Deduction

The Contractor shall be entitled to deduct from, or set off against, any money due from him to the Subcontractor any sums which the Subcontractor shall be liable to pay the Contractor whether such liability is incurred in connection with the works forming part of this Subcontract or occasioned in any other manner whatsoever related to this Subcontract Agreement.

5.3.4 Removal of Subcontractor’s Employee

The Contractor

representative

any

6. The “

6.1 Subcontractor’

The

Contractor for

Subcontract

of construction

for consent.

6.2 Subcontractor’

The

subcontractors

execution of the Main Contract. The Subcontractor shall not be allowed to claim any extension of time for completion and any additional cost whatsoever in nature incurred by the lack of cooperation among the Subcontractors employed by the Contractor. In case of any delay in the Subcontractor Works due to the fault of the Subcontractor, which result in delay in other Subcontractor’s and / or the Contractor’s works, the cost of such delays shall be fully compensated by the Subcontractor.

6.3 The Third Party Liability of the Subcontractor 商承担。

6.3分包商的第三方责任

关于分包工程,要求分包商采取一切必要的安全措施。由于分包商的疏忽大意及分包商人员不当的行为对其活动周围的第三方人员及财产或者公共设施管线造成的任何损害,此类损害由分包商独立承担、费用自理。

6.4遵守指示

合同3.4条工期的延期,则履约保函有

效期应该得到相应的延长。

7.3履约保函的返还

分包合同的缺陷责任期满,并且分包工

程得到业主颁发的竣工证书后将返还

分包商的履约保函。

8.分包价格

8.1分包价格

The Subcontractor is required to take all the necessary safety measures regarding its Works. The Subcontractor shall be solely responsible for any damage to third parties, properties or to the utility lines, due to negligence, carelessness and misappropriate handling of the Subcontractor’s personnel, in the vicinity of its operations and the cost of such damage shall be borne by the Subcontractor.

6.4 Obey Instruction of the Contractor and Engineer The Subcontractor shall fully comply with the instructions of the

Employer for

execution of the

occurred between

Works of the

subcontractor, then

instruction of the

disputes.

Within 21

Acceptance

Contractor a

amount equal

the form of

period of the Subcontract Works, and which shall also be required to extend as the time extension of Subcontract Works as defined in Clause 3.4.

7.3 Release of Performance Guarantee

This Performance Guarantee can be returned to the Subcontractor as the completion of the Defect Liability Period and also the Performance 中标通知书涉及的分包工程合同额是根据本分包工程协议附件BOQ中的每个细目的工程量及固定单价计算得出的。最终的分包价格应由分包商实际完成并由咨询工程师和业主批准并由承包商审核的工程量和本分包协议BOQ中的固定单价计算得出,作为分包工程的最终付款证明,签发分包工程

及其它由任何政府部门征收的其它费用,包括联邦政府,省政府,以及地方政府。这包括对分包合同工程征收的费用,还包括对因为使用设备,供应品,材料,或者劳工来实施分包合同。

9.支付

9.1 动员预付款

9.1.1 动员预付款的支付:

根据分包商的要求,承包商可向分包商支付分包合同金额%的动员预付款,条件是

Certificate of the Subcontract Works has been

issued by the Employer.

8.The Subcontract Price

8.1 The Subcontract Price

The specified sum of the Subcontract Price as mentioned in the Letter of Acceptance and which calculated in accordance with the fixed unit rates set out against each item in the Bill of Quantities appended hereto this

Subcontract price

fixed unit rates

by the

Contractor shall

Clause 9.4 of this

The unit price of

cost for execution

completion of the

material,

security, income

Any item of work

shall be considered as included in other rates and prices in the Bill of Quantities and will not be paid for separately, except the Engineer has approved a new rate through variation and then the Contractor make valuation to approve or reject accordingly, if any new price is approved then the Contractor shall first hold/deduct 20% overhead from the approved amount (which tax has been deducted) then shift to the Subcontractor.

8.2 Taxes

The Subcontractor shall pay all taxes, freight, customs duties, import duties, business taxes, sales taxes, 分包商须承包商提供一个不可撤销、无条件的预付款保函,其保函应该从承包商认可的银行开具。预付款金额的%将在分包商全面进场后进行支付,剩余%预付款金额将在现场施工已经开展并得到承包商的认可后28天内支付。

9.1.2 动员预付款的返还(如有)

妥善保存,并不得用于本工程以外的其他项目。

9.2.2 材料预付款的计算

金额按出厂材料价格X经承包商认可的进场数量的金额的75%进行计算,并附相应的厂家出具的发票、检验报告等证明凭证。

9.2.3 材料预付款的支付

经承包商/咨询工程师批准的材料预付

income taxes, contributions duties or other chargers of any kind levied by any authority or governmental body including, Federal Government, Provincial Governments and local bodies on or because of the Subcontract Works to be performed, or on or because of the use of equipment, supplies, materials or labours in the performance of the Subcontract.

9.Payment

9.1 Mobilization Advance

9.1.1 Payment of Mobilization Advance

At the request of the Subcontractor, the Contractor will make a sum of

unconditional Bank

the Contractor, the

first % amount of advance payment shall be paid to

then the

Subcontractor

The mobilization

of the subcontract

assure that the

Guarantee should

recovered and

advance fully

The supplied material is used for incorporated in the permanent work and which not easy be inclined to become erosion or occur other chemical reaction, or the material is listed under the Main Contract as payable for material advance, then the Contractor may consider to make material advance payment.

9.2.1 Terms and Conditions of payment:

a) The material has been delivery to site and obtained approval from Engineer/Contractor;

b) The purchase scheduled quantity has been approved by the Contractor;

款,将计入“第9.4中期账单”支付。

9.2.4 材料预付款的扣回

当材料用于永久工程后或承包商认为

的其他原因,该材料预付款将在中期账单中进行扣回。

9.3调差

承包商认为分包商所接受的单价已经充分考虑在施工期间由于市场价格的浮动而产

的5%,如不足将转入下次账单进行支付。

(b)承包商收到业主相应的计量款后将在28天内对分包商进行支付。

9.5 最终账单

9.5.1 最终账单的准备及提交

在分包工程交工后,分包商依据现场实际完成、由咨询/业主/承包商批复的工程提交其最终账单,该完成工程必须严格按照分包合

工程分包合同范本

工程专业分包合同范本 发包方:_________________(以下称甲方) 分包人:_________________(以下称乙方) 根据《中华人民共和国合同法》、《中华人民共和国建筑法》等相关法律法规及甲方的有关规定,结合本工程的具体情况和特点,为明确甲乙双方在施工中的权利、责任和义务,经双方友好协商,达成如下协议; 一、工程概况 分包工程名称:_____________工程防水工程 分包工程地点:工程承包范围:屋面防水卷材及基层处理所需的人工、材料、机械、包质量、包工期、包安全及现场文明施工。分包方式:包单价、包人工、包机械、包质量、包安全、包工期、包文明施工、包环境保护。 二、工期 1.按甲方确定的进度计划要求工期。 2.施工过程中,乙方必须严格按甲方制订的进度计划,确保各节点计划的完成。 3. 如由于甲方的原因,工期可以延续(必须经甲方项目经理确认为准,其他人员确认无效),但乙方必须采取积极的赶工措施,确保规定竣工时间的实现。 4. 其他工期延误和顺延约定:出现不可抗力(不可抗力:指不能预见、不能避免并不能克服的客观情况。不可抗力的判别以当地电台、电视台报导为准。一天以上台风,暴雨;由市政府规定的停止施工的各项条件);工期经甲方签字认可后可相应顺延。 四、工程质量标准 本分包工程质量标准双方约定为:一次性验收合格。 6.语言文字和适用法律、行政法规及工程建设标准 6.1本合同使用_汉语_语言 6.2本合同需要明示的法律、行政法规和规章:本合同文件的适用法律是中国和吉林省,法规,及合同文件规定的部门法律、法规。 7.图纸 7.1甲方向乙方提供图纸的日期;本合同经双方签字盖章生效后一周内。 甲方向乙方提供图纸的套数; 1套。 五、双方一般职责 8.甲方代表 姓名:___________ 电话:___________ 9.乙方项目经理 姓名:___________ 电话:___________ 10.甲方职责

分包工程合同标准样本

合同编号:WU-PO-547-29 分包工程合同标准样本 In Order T o Protect The Legitimate Rights And Interests Of Each Party, The Cooperative Parties Reach An Agreement Through Common Consultation And Fix The Responsibilities Of Each Party, So As T o Achieve The Effect Of Restricting All Parties 甲方:_________________________ 乙方:_________________________ 时间:________年_____月_____日 A4打印/ 新修订/ 完整/ 内容可编辑

分包工程合同标准样本 使用说明:本合同资料适用于协作的当事人为保障各自的合法权益,经过共同协商达成一致意见并把各方所承担的责任固定下来,从而实现制约各方的效果。资料内容可按真实状况进行条款调整,套用时请仔细阅读。 订立合同双方: ____,以下简称总承包方: ____,以下简称分包方。 双方根据分工负责、配合协作的精神,共同完成____工程之建筑安装任务,经充分协商,特订立本合同。 第一条工程名称 _______.(指分包部分之工程名称) 第二条工程地点 第三条工程范围 _______.(可用列附表办法)

第四条质量标准 _______.(可依照工程施工详图、施工说明书及《安装工程施工验收技术规范》列出) 第五条承包方式 _______(如按预算实行包工包料,属于总承包人及发包方负责供应之材料,分包方应将材料品种、规格、数量、交货时间、技术要求等用附表详细注明)。 第六条工程总价 本工程包价计人民币____元整。 第七条工程包价 本工程包价计人民币____元整(本工程全部总造价减去发包人及总承包方供应材料总值)。 第八条付款办法 第九条工程期限

(完整版)软件技术服务分包合同(模板)

技术服务分包合同

技术服务分包合同 该技术服务分包合同(下称“本合同”)于____年__月__日(下称“生效日”), 由以下双方签订: 上海xxxx有限公司(下称“甲方”) 联系地址:x 电话: 传真: 上海xxx有限公司(下称“乙方”) 联系地址: 电话: 传真: 依照《中华人民共和国合同法》等有关法律、法规,甲乙双方本着友好合作、互助互利的原则,双方协商一致,签订本合同: 1.分包义务 1.1.乙方应按照本合同条款和条件提供“专业服务”及“工作清单”中所描述的“交付物”。 1.2.“工作”应按照附件规定的期限完成。除非另有书面协议,时间是本合同的关键,乙方 应按照甲方的项目规定期限或阶段交付“工作”,并使其符合甲方的检验要求。如果某阶段的工作因任何原因被延误,乙方应其最大努力挽回延误的时间。 1.3.除非另有约定,“专业服务”应在甲方正常工作时间提供,乙方应在每阶段结束时向 甲方提交完成工作的记录。 1.4.乙方,包括其雇员、工作人员或代理,在甲方或客户的场所内应遵守其规章、守则及 包括保安措施在内的要求。 1.5.除因完成“工作”而必需进入的场所外,未经甲方事先许可,乙方包括其雇员、工作人 员或代理,不得进入客户的任何场所。 1.6.如甲方认为乙方(或其雇员、工作人员或代理)自身行为不当或已无法履行其职责,乙 方(或其雇员、工作人员或代理)在收到通知后,应立即撤离客户的场所。在此情况下,如果甲方认为必要,甲方可聘用其他人员完成“工作”,由此发生的额外费用由乙方补偿。

1.7.甲方针对本第1条事项所作出的决定是最终的和结论性的。 2.工作义务 2.1.甲方将为乙方提供为完成“工作”所必需的信息、数据、文档、用机时间、设施、工 作场地和办公条件。 2.2.甲方将为乙方提供专业而及时的联络,并将在约定的时间定期检验工作进程,解决相 关的问题。 2.3.甲方可向乙方出借物品供其在提供服务时使用,但双方应为此签署一份设备出借合 同。除非在该出借合同中另有规定,出借的物品应在“工作”完成时归还。 3.支付条款 3.1.合同总额为_________________元。未经事先书面同意,乙方无权代表甲方发生任何费 用。 3.2.“工作”完成后,乙方应按合同总额开具发票,甲方将收到发票后网银付款。本合同 项下甲方所支付的款项包含所有适用的税项。 4.验收与维护 “工作”应按照附件规定的日期交付验收,届时甲方将进行验收测试以确认“工作”是否符合“工作清单”中详细规定的标准。如果“工作”未通过验收,甲方将作出以下选择: 4.1.拒绝接收“工作”。 4.2.降价接收“工作”。 4.3.要求乙方修正缺陷后再提交甲方验收,此时乙方将自费进行必要的修正并在双方同意 的期限内再次交付验收。 乙方应对所承担的“工作”有维护的义务,维护时间应按照双方约定的来执行。 4.4.免费维护时间: 4.5.收费维护时间: 5.知识产权归属 5.1 本合同项目技术成果的专利申请权、计算机软件的著作、技术秘密以及技术资料等知识产权归甲方所有。同时乙方同意放弃以上知识产权的署名权并同意甲方对其进行任何形式的修改。 5.2 乙方不得在向甲方交付研究开发成果之前,将研究开发成果及非专利技术泄露或转让给第三方。

工程分包合同范本2018专业版

工程分包合同范本2018 专业版 (文中蓝色字体下载后有风险提示) 甲方(承包人): 乙方(分包人): 风险提示: 分包合同条款内容应当规范、具体、具备可操作性,否则,如果承包人、分包人的合同水平和法律意识都比较低或差异大时,则订出的合同内容不全,权利义务不均衡,那么这些都在以后施工过程中产生的纠纷埋下伏笔,在订立分包合同时,可以咨询专业律师,避免某些条款遗漏,或者设计不严谨,造成不必要损失。 按照《中华人民共和国合同法》《中华人民共和国建筑法》及其他有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,甲方将------ - 工程的所有项目的施工任务交由乙方完成,经协商一致签订本合同。 第一条、工程概况 1、工程名称: 2、工程地点: 风险提示: 允许分包的工程范围应当在依据招标文件,分包的工程不得超过总工程量的 30%。各项专业工程分包的总量超过承包人合同工程总量的 30%的,或者专业工程分包管理费超过 30%的(招标文件规定的税费除外),这是底线,逾越底线均认定为违法分包。同时,这里也强调分包工程不得再次分包,凡再次分包也被认定为违法分包。 另外,建设工程主体结构的施工必须由承包人自行完成,承包人如果存在违法分包的工程,当出现不符合规定的质量标准造成的损失,那么承包人也应当承担连带赔偿责任。 3、分包工程范围: 4、承包形式: 5、工程期限: 计划开工日期:年月日,计划竣工日期:年月日,合同总工期为日。 6、质量等级: 第二条、本合同条款符合总承包合同的要求 第三条、甲乙双方的权利、义务 1、甲方的权利与义务 (1)对乙方承担施工任务的质量、安全、进度情况的监督、检查;督促

项目分包合同范本

项目分包合同范本 发包方:吴伟明项目部(以下简称甲方) 承包方:李中午(以下简称乙方)身份证号码:342830************ 依照《中华人民共和国合同法》、《劳动法》、《中华人民共和国建筑法》及其相关规定,为了明确甲乙双方的权利和义务,确保工程项目的顺利施工,保障双方的合法权益,根据本工程的具体情况,经双方协商达成一致,特签订以下协议: 第一条:工程名称:泰宸沙河名苑三期19#、20#、24#~26#房 第二条:工程地址:华江路西、爱特路北 第三条:工程范围和内容: 木工班施工范围内容:①基础(包括基础部分修土)、主体以及二次结构涉及到模板制作安装。②人货电梯、塔吊基础以及其他设备

模板制作安装。③跑模、凿除,由乙方处理(如在甲方规定的时间内乙方不及时处理的则甲方另行安排其他班组去处理,处理费用在乙方的结算款中扣除)。④预制构件木模制作。⑤货梯跑道板铺设,电梯井道板铺设,楼层预留洞铺设。⑥生活区临时房木工生活。⑦施工现场道路模板、场地模板、挑架底部封板等。⑧使用材料的运输和施工区域内的清理,场外材料运进卸车、场内运输搬运。⑨配合本项目所需达到标化文明施工要求的工作及自身本职工作范围内的场地、材料落手清工作;接到通知6小时内必须派人实施,否则由项目部派人实施费用从工程结算款中扣除。⑩派专人配合结构层每层的放样、弹线工作、卸料平台安装工作。○11木工班组用机械及辅材(小电箱(二相及三相拖线箱)、劳动车、太阳灯及灯管、平刨机、电焊机及电焊条、圆盘机、切割机及切割片、三型卡、一般螺杆及止水螺杆(包括割除)、套管、铁钉、铁丝、模板中的水泥支撑、安全帽、扫帚等及自带机械的一切保养及维修)由乙方负责○12图纸的增减工程一律不作任何调整。○13包括为了达到优质结构工程所有木工范围内的工作、及达到文明标化工程本工地木工班需做的所有工作在内,不另计点工。 第四条:工程质量 乙方必须严格按国家现行施工规范和有关国家、地方标准图集和设计的施工图及项目部技术交底施工,施工过程中严把质量关,做好

建筑安装工程分包合同样本(官方版)

编号:QJ-HT-0554 建筑安装工程分包合同样本 (官方版) Both parties shall perform their obligations as agreed in the contract or in accordance with the law within the term of the contract. 甲方:_____________________ 乙方:_____________________ 日期:_____________________ --- 专业合同范本系列下载即可用---

建筑安装工程分包合同样本(官方版)说明:该合同书适用于甲乙双方为明确各自的权利和义务,经友好协商双方同意签署合同,在合同期限内按照合同约定或者依照法律规定履行义务,可下载收藏或打印使用(使用时请先阅读条款是否适用)。 订立合同双方: ____,以下简称总承包方:____,以下简称分包方。 双方根据分工负责、配合协作的精神,共同完成____工程之建筑安装任务, 经充分协商,特订立本合同。 第一条工程名称 ____。(指分包部分之工程名称) 第二条工程地点 ____。 第三条工程范围 ____。(可用列附表办法) 第四条质量标准

____。(可依照工程施工详图、施工说明书及《安装工程施工验收技术规范》列出) 第五条承包方式 ____(如按预算实行包工包料,属于总承包人及发包方负责供应之材料,分包方应将材料品种、规格、数量、交货时间、技术要求等用附表详细注明)。 第六条工程总价 本工程包价计人民币____元整。 第七条工程包价 本工程包价计人民币____元整(本工程全部总造价减去发包人及总承包方供应材料总值)。 第八条付款办法 第九条工程期限 按本合同第三条规定的工程范围自__年__月__日开工至__年__月_ _日止全部完工。 第十条中间交工

最新版项目服务分包合同模板

合同编号: 【】项目 《服务分包合同》 由 【甲方公司名称】 与 【乙方公司名称】 签订地:【】

该《服务分包合同》(以下简称为“本合同”)由以下各方于【】年【】月【】日(“生效日”)于【签订地】签订: 【】(下称为“甲方”),注册地址位于【】,与 【】(下称为“乙方”),注册地址位于【】,统一社会信用代码:【】。 前言: (a)甲方承接了_____________(下称为“客户”)的项目(下称为“项目”); (b)甲方期望将项目的部分服务工作分包给乙方完成,而乙方保证能够向甲方提供本合同项下的服务; 依据中华人民共和国有关法律和法规,双方经友好协商,就甲方向乙方采购本合同项下服务之事宜,订立本合同。 【合同正文】 1合同用语约定 除非合同条款或上下文另有所指,否则本合同中下列用语的含义是: “服务”是指本合同中约定的由乙方提供的开发、设计、研究、安装、咨询、绘制、技术支持、维护保养、培训、巡检或保修等服务和工作。 “服务人员”是指具体实施服务的人员。 “项目”:是指本合同前言部分中所提及的项目。 “客户”:是指本合同前言部分中所提及的甲方的项目客户。 “现场”:是指履行服务的场所。 “交付物”是指任何由乙方提交的与本合同有关的文档、报告、建议、计算机软件、代码、设备、产品、资料、地图或数据等。 “保修期”:是指对交付物予以的免费修理或更换的质量保证期间。 “不可抗力”:是指双方不能合理预见和避免的客观事件和自然事件,包括地

震、台风、洪水、战争、突发性公共卫生事件和政府行为等。 “法律”:在本合同中应理解为包含所有适用的法律、行政法规、部门规章、地方规章、政府规范性文件。 “再分包”:是指经甲方事先同意后,乙方将本合同项下的服务转包、分包予第三方。该第三方称为“再分包商”。 “包含”或“包括”:在本合同中应视为“包括,但并不限于”。 2合同组成 2.1本合同由以下部分组成:正文部分;附件A《商务条款》;附件B《服务 说明书》;附件C《项目服务进度报告》;附件D《保密协议》(可选)。 2.2当附件与本合同正文部分的约定发生冲突的,以附件的效力优先。 3服务 3.1服务:乙方应当选派专业的服务人员以勤勉尽责的态度履行本合同中约定的 服务工作。乙方提供的服务不符合本合同约定的,乙方应负责重做并赔偿甲方和客户因此产生的损失。 3.2进度:乙方应当严格按照本合同约定的进度按时提供服务。服务进度延误的, 乙方应按照本合同的约定承担逾期责任。 3.3现场管理:如乙方在甲方或客户提供的场所提供服务,或者进入上述场所, 乙方应当严格遵守甲方和客户的管理和要求,包括安保、环保、消防、卫生、网络管理、保密等方面。因服务人员的故意或过失导致甲方或客户发生人身或财产损失的,乙方应当予以赔偿。 3.4工具:乙方应自备完成服务所需要的软、硬件工具。如果甲方或客户提供了 服务工具,则乙方应当妥善使用,在使用完毕后完好归还工具。 3.5亲自履行和再分包:除非甲方事先书面同意乙方再分包,乙方应当亲自履行 本合同项下的全部服务。即使甲方同意再分包,亦不免除乙方的合同义务和责任,乙方仍需对全面、正确履行本合同项下的全部服务承诺向甲方承担直接的合同责任。 3.6服务人员: (a)乙方保证服务人员与乙方之间建立并在本合同有效期内维持合法的

工程分包协议书范本通用版

编号:_______________ 本资料为word版本,可以直接编辑和打印,感谢您的下载 工程分包协议书范本通用版 甲方:___________________ 乙方:___________________ 日期:___________________

甲方(承包人): 乙方(分包人): 依照《民法典》、《中华人民共和国建筑法》及其它相关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,承包人和分包人双方就分包工程施工事项经协商达成一致,订立本合同。 一、工程名称: 二、分包工程范围: 三、工程单价: 四、质量要求:按设计和施工规范进行施工,质量达到优良。 五、工期要求:按业主要求工期: 开工日期________年___月___日,竣工日期________年___月___日,合同总工期为_____日。 六、安全要求:乙方对施工安全负责,在施工中严格按施工安全生产规范进行,做到安全生产无事故。 七、结算方式:工程竣工验收三十日内,乙方提交结算材料,甲方予以审核结算。 八、付款方式:甲方按业主工程施工计量认证后的拨款额_____%支付乙方工程款,工程完工后支付乙方工程款为业主拨付额的_____%,余款待工程竣工验收合格后按业主拨款额结算。 九、指令和决定 1、就分包工程范围内的工作,承包人随时可以向分包人发出指令和决定,分包人应执行承包人发出的所有指令和决定。 2、就分包工程范围内的工作,分包人应执行经承包人确认和转发的建设单位或监理单位发出的所有指令和决定。如分包人与建设单位或监理单位发生直接工作联系,将被视为违约,并承担违约责任。 十、承包人驻工地代表

建设工程施工总分包合同(合同示范文本)

( 合同范本 ) 甲方: 乙方: 日期:年月日 精品合同 / Word文档 / 文字可改 建设工程施工总分包合同(合同 示范文本) The clear rights and obligations of both parties facilitate the cooperation of both parties, provide a basis for resolving disputes in the future, and prevent possible risks.

建设工程施工总分包合同(合同示范文本) 第一部分协议书 发包人(全称):__________________ 承包人(全称):__________________ 分包人(全称):__________________ 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其它有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,鉴于__________ (以下简称为“发包人”)与承包人已经签订施工总承包合同(以下称为“总包合同”),承包人和分包人双方就分包工程施工事项经协商达成一致,订立本合同。 一、分包工程概况 分包工程名称:____________________ 分包工程地点:____________________

分包工程承包范围:________________ 二、分包合同价款 金额:大写:人民币________________元, 小写:_________________元。 三、工期 开工日期:本分包工程定于_______年______月________日开工;竣工日期:本分包工程定于_______年______月________日竣工;合同工期总日历天数为:_________天。 四、工程质量标准 本分包工程质量标准双方约定为:____________________ 五、组成分包合同的文件包括: 1.本合同协议书; 2.中标通知书(如有时); 3.分包人的报价书; 4.除总包合同工程价款之外的总包合同文件; 5.本合同专用条款;

服务承包合同范本

服务承包合同范本 在[雇主姓名]为一方(以下称雇主)与[服务承包者姓名]为另 一方(以下称服务承包者)之间于一九年月日达成本合同(连同份所附的并构成本合同一部分的附件) 鉴于雇主依据本合同要求服务承包者提供服务(以下称服务) 和服务承包者同意按在本合同中所规定的条款和条件提供服务现双方达成如下协议: 第一条总则 1.01定义 除非上下文另有要求下列词汇一旦用在本合同中具有下列含义:(a)“合同”是指由雇主和服务承包者签定的合同按由双方签字的合同格式加以记载其中包括全部附件和附录以及以参考资料形 式列入的全部文件 (b)“服务承包者”是指其执行服务的建议已被雇主接受的人或公司 (c)“雇主”是指其雇用服务承包者执行服务的一方 (d)“由雇主提供的支持”是指由雇主为服务承包者执行合同项下的服务而提供的数据、服务、设备以及便利 (e)“一方”是指雇主或服务承包者视情况而定而“双方”是指他们二者 (f)“人月”是指相当于一(1)个日历月期限的服务其以在176个工作小时提供这样的服务的人为依据

(g)“人员”是指作为雇员由服务承包者或其分包者所雇用并被分配执行服务或其任何部分的人员 (h)“服务”是指由服务承包者根据合同所实施的工作 第二条服务 2.01服务的范围 服务承包者将依据在附件中所阐明的职责范围(tor)/工作说明(sow)的最终条款和本合同所有其它要求执行服务 2.02服务的标准 服务承包者将利用其专门的技术完成他在本合同项下的义务并依据在tor/sow里所规定的或在中华人民共和国另外普遍适用于合同所要求服务类型的最高职业、技术和质量标准提供服务服务承包者将认真负责地履行其义务并将时时刻刻为雇主的利益而工作为了达到这些目的经雇主的同意服务承包者将应提供具有充分素质和经验的人员并为圆满完成服务提供所需的人数关键人员的简历作为附件的附录附上并构成本合同的一部分 2.03估计的人月数 双方同意服务承包者将依照作为附件附于合同的工作计划执行服务为了执行他在本合同项下的义务服务承包者将提供总人月数为的服务除非经双方另行同意服务承包者将没有义务提供超过上述总人月数的服务 2.04附加服务

专业分包合同范本

110千伏XX变电配套线路工程(电缆部分及架空部分)(土建部分)分包合同 承包人:XX市输变电工程公司 分包人:南方送变电有限公司 签署地点: 110千伏输变电配套线路工程(电缆部分及架空部分)(土建部 分) 第一部分协议书 承包人(全称):XXX市XX输变电工程公司 分包人(全称):XXX省XXX市南方送变电有限公司 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其它有关法律、

行政法规,遵循平等、自愿、公平和诚实信用的原则,鉴于XX电网公司XX供电局 (以下简称为“发包人”)与承包人已经签订施工总承包合同(以下称为“总包合同”),承包人和分包人双方就分包工程施工事项经协商达成一致,订立本合同。 一、分包工程概况 分包工程名称:110千伏XX输变电配套线路工程(电缆部分及架空部分)(土建部分) 分包工程地点:XX市XX镇 分包工程承包范围: 1.工程主要包括(但不限于)以下内容(具体按施工图纸、招标文件及供电局要求施工): 1.1 架空部分专业工作主要包括(但不限于): 1.1.1 本工程架空部分的土石方工程; 1.1.2 本工程架空部分的基础工程; 1.1.3 架线工作、施工道路、临时施工用地、接地线铺设及竣工后植被恢复; 1.1.4 桩基检测费; 1.1.5 材料卸车保管费等; 1.2 电缆部分专业工作主要包括(但不限于): 1.2.1 双回路砼电缆沟1884米,每隔25米设臵一个沟间直通工作井; 1.2.2 新建双回8线埋管634米,每隔20米设臵一个直通工作井; 1.2.3 新建双回8线顶管305米; 1.2.4 新建管(顶管、埋管)沟间直通工作井27个; 1.2.5 新建90°工作井4个; 1.2.6 新建中间接头井4个; 1.2.7 电缆终端场一处等; 1.2.8 包括施工临时占地、围护栏、甲供材卸车保管费、白蚁防治、电缆线路标志桩等; 1.3 安全措施费及文明施工费(¥36,560元,已包含在工程限价内); 1.4 为完成工程发生的有关费用; 1.5 材料归属: 1.5.1 本工程供电局提供清单上的材料; 1.5.2 甲方提供¥1,398,535元钢筋、混凝土及顶管管材的工程施工材料; 1.5.3 非上述约定材料由乙方负责。 二、分包合同价款 金额:大写:人民币伍佰壹拾万玖仟壹佰元整,小写:¥5,109,100.00元 三、工期 开工日期:本分包工程定于 2011年11 月1日开工; 竣工日期:本分包工程定于2012年6月30日竣工;

工程分包合同样本

建设工程施工分包合同

发包人:浙江华新建筑工程有限公司(以下简称甲方)承包人:(以下简称乙方)根据《中华人民共和国合同法》以及有关法律、法规的规定,为明确双方的权利义务,保证双方的合同目的得以实现,经双方协商一致,订立本合同,据以共同遵守。 一、工程概况 1、工程名称:浙江杭州金富春丝绸化纤有限公司5号厂房 2、工程地点:富阳市富灵路100号 3、工程内容:土建、安装及附属工程 二、工程承包范围 承包范围:土建、安装及附属工程 三、合同工期 根据工程需要,绝对工期为365 天(日历天),即2012 年 3 月4日前完工,具体工程进度要求依甲、乙双方与建设单位共同确定的进度计划为准。 四、质量标准及技术要求: 1、材料尺寸符合图纸要求材质符合国家标准。 2、质量达到“合格”,且保证通过政府检验部门检验。 五、工程管理费用收取标准及结算方式 1、工程管理费用收取标 经协商,甲方向乙方收取工程直接费的8%作为管理费、税金、利润等一切费用。工程取费根据当地相关取费定额及甲方(总包方)与建设方的协议执行。 2、结算方式 按浙江省2008年建筑工程定额及相关配套文件,工程按施工图及联系单结算,材料按施工期当地定额站发布的信息价。 四、工程费用支付及保证金 1、工程费用支付 根据建设方提供的配套工程施工图,由乙方做出预算,乙方垫资施工至±0后十日内甲方支付乙方已完成工程量的75%;以后甲方按每月已完成工程量的75%支付给乙方;主体结构封顶后甲方付至乙方工程预算总造价75%的工程款;在竣工验收合格后,乙方向甲方提供完整竣工结算资料十日内进行竣工结算,竣工结算完毕双方认可后十日内付至工程总价的85%;竣工决算审核期按《通用条列》执行。工程决算经建设方审核及审计机构审定定案后,除扣留3%的工程质保金外,其余款项在三十日内结清,保修金返还按国家规定无息返还。 2、保证金 乙方进场施工十日内向甲方交纳30万元保证金。保证金在工程竣工验收合格后十日内无息返还。 六、组成合同的文件 合同文件组成及解释顺序:1、双方有关工程的洽商、变更等书面补充协议或文件 2、本合同文件 3、标准、规范及有关技术文件 4、图纸 5、工程预算书 6、合同履行过程中,工程例会、会议纪要等视为本合同的组成部分。 七、双方权利和义务 1、甲方派驻的工程师姓名:朱建富职务:总工程师职权:工程师 乙方项目经理姓名:职务: 2甲方工作 1、提供乙方所需设计图纸、建筑平面图及有关技术文件等作为乙方产品设计、生产和施工的有效依据,乙方设计完成后,由甲方签字确认后方可制作或施工。

建设工程施工专业分包合同样本(官方版)

编号:QJ-HT-0448 建设工程施工专业分包合同 样本(官方版) In order to clarify their rights and obligations, sign contracts to ensure that their legitimate rights and interests are not harmed. 甲方:_____________________ 乙方:_____________________ 日期:_____________________ --- 专业合同范本系列下载即可用---

建设工程施工专业分包合同样本(官 方版) 说明:该合同书适用于甲乙双方为明确各自的权利和义务,经友好协商签署合同,在合同期限内按照合同规定或者依照法律规定履行义务,保证权利双方合法权益不受损害,文档可下载收藏或打印使用(使用时请先阅读条款是否适用)。 承包人:_____ 分包人:_____ 一、词语定义及合同文件 1.词语定义 1.1 通用条款:是根据法律、行政法规规定及建设工程施工的需要订立,通用于分包工程施工的条款。 1.2 专用条款:是承包人与分包人根据法律、行政法规规定,结合具体工程实际,经协商达成一致意见的条款,是对通用条款的具体化、补充或修改。 1.3 发包人:指在总包合同协议书中约定的具有工程发包主体资格和支

付工程价款能力的当事人,以及取得该当事人资格的合法继承人。 1.4 承包人:指在总包合同协议书中约定的,被发包人接受的具有工程施工总承包主体资格的当事人,以及取得该当事人资格的合法继承人。 1.5 分包人:指在本分包合同协议书中约定的,被承包人接受的具有分包该工程资格的当事人,以及取得该当事人资格的合法继承人。 1.6 总包工程:指由发包人和承包人在总包合同协议书中约定的承包范围内的工程。 1.7 分包工程:指由承包人和分包人在本合同协议书中约定的分包范围内的工程。 1.8 工程师:指在总包合同中约定的由工程监理单位委派的工程师或发包人指定的履行总包合同的代表,其具体身份和职权由发包人和承包人在总包合同专用条款中约定。 1.9 项目经理:指承包人在总包合同专用条款和本合同专用条款中指定的负责施工管理、履行总包合同及本合同的代表。 1.10 分包项目经理:指由分包人在分包合同专用条款中指定的负责施工管理和履行分包合同的代表。

项目分包合作协议

中铁建沈阳地铁9号线项目分包合作协议 甲方:公司 营业执照号: 注册地址:法定代表人: 职务:身份证号: 乙方: 营业执照号: 注册地址:法定代表人: 职务:身份证号: 甲乙双方本着优势互补、互利互惠的原则,为了更好地开拓市场,扩大企业的经济效益和社会效益,甲乙双方经过平等协商,就双方分包合作一事达成如下协议。 第一条分包合作内容 1.1经双方协商,一致同意在分包合作有效期内,乙方可以以甲方名义,从事甲方经营许可证范围内的经营项目。乙方可以以甲方单项资质去参加乙方内部招投标、承接和完成工程。 1.2乙方以甲方资质承接的工程由乙方独立施工,甲方向乙方收取人民币元整或工程总造价 %,作为分包合作费。 1.3乙方利用甲方名义所开发票,则乙方需向甲方缴纳所需开具增值税专用发票面值金额的 %(应纳增值税额=开票金额÷(1+3%)×3%)。 1.4分包期间,乙方承接的工程项目所涉及的工程款项应全部转入甲方指定的银行帐户,待扣除税金及管理服务费后其余工程款三日内转给乙方,工程建设方直接以现金或其他方式支付给乙方的工程款,乙方应及时通知甲方。 第二条甲方的基本权利和义务 2.1按照本协议的约定向乙方收取分包合作费; 2.2在分包合作期限内,向乙方提供营业执照、资质证书、法人委托书等证明文件,并积极配合乙方完成相关工作。

2.3对乙方在经营过程中提出的合理要求,包括但不限于上岗人员配备、发票开具及涉税事项、项目施工事项等尽可能提供良好周到的服务。 第三条乙方的基本权利和义务 3.1乙方有权以甲方名义,从事甲方经营许可证范围内的单项资质经营项目。 3.2乙方有权以甲方资质去参加乙方内部招投标、承接和完成工程。乙方承揽工程项目的债权债务、工程质量及聘用人员的人身安全均由乙方承担。乙方应按本协议约定向甲方足额缴纳管理服务费及相关税费。 3.3乙方以甲方名义承接和实施的工程在经营上实行内部独立核算,自负盈亏。 3.4乙方以甲方名义承接和实施的工程一切正常利润归乙方所有,处置分配不受甲方干涉。 3.5乙方在经营活动中严格遵守国家法律法规和甲方规章制度。 3.6相关经营条件及施工设备乙方自主负责解决。 3.7认真负责进行施工项目的质量和安全,对发生的质量问题和质量、安全事故乙方负完全责任。乙方因在施工过程中管理不善而导致的质量、安全问题和瑕疵所导致的返工及损失,均由乙方独自承担,与甲方无关。 3.8乙方应维护甲方的信誉和形象,不做任何假冒、欺诈、侵权、损誉的事情。 3.9甲方向乙方提供承接工程业务所需要的有关资料,协助乙方办理工程协议签订,凡须由施工单位负责缴纳的费用和资料等有关费用均由乙方负责。乙方需甲方提供企业相关经营资料(企业营业执照、资质证书、组织机构代码证、税务登记证、法人授权委托书等)原件时,乙方应向甲方缴纳。在乙方持有甲方企业经营资料期间,乙方应妥善保管甲方资料,不得擅自转给他人使用,转给他人使用所产生的一切责任由乙方承担;若有遗失,应及时通知甲方、登报告声明并承担由此产生的责任及费用。在双方约定期限内,乙方无违反本款之行为并退还甲方企业相关经营资料的,甲方应及时退还押金 第四条分包合作有关事项的约定

专业分包合同范本

110 千伏XX 变电配套线路工程(电缆部分及架空部分)(土建部分)分包合 同 承包人:XX 市输变电工程公司 分包人:南方送变电有限公司 签署地点:

110 千伏输变电配套线路工程(电缆部分及架空部分) 土建部 分) 第一部分协议书 承包人(全称):XXX市XX输变电工程公司 分包人(全称):XXX省XXX市南方送变电有限公司___________________________ 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其它有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,鉴于XX电网公司XX供电局(以下简称为"发包人"与承包人已经签订施工总承包合同(以下称为"总包合同",承包人和分包人双方就分包工程施工事项经协商达成一致,订立本合同。 一、分包工程概况 分包工程名称:110千伏XX输变电配套线路工程(电缆部分及架空部分)(土建部分) 分包工程地点:XX市XX镇 分包工程承包范围: 1. 工 程主要包括(但不限于)以下内容(具体按施工图纸、招标文件及供电局要求施工): 1.1架空部分专业工作主要包括(但不限于): 1.1.1本工程架空部分的土石方工程; 1.1.2本工程架空部分的基础工程;

1.1.3架线工作、施工道路、临时施工用地、接地线铺设及竣工后植被恢复; 1.1.4桩基检测费; 1.1.5材料卸车保管费等;1.2电缆部分专业工作主要包括(但不限于):

1.2.1 双回路砼电缆沟1884米,每隔25 米设置一个沟间直通工作井; 1.2.2 新建双回8 线埋管634米,每隔20米设置一个直通工作井; 123新建双回8 线顶管305米; 124 新建管(顶管、埋管)沟间直通工作井27个; 1.2.5 新建90 °工作井4 个; 126 新建中间接头井4 个; 1.2.7 电缆终端场一处等; 1.2.8 包括施工临时占地、围护栏、甲供材卸车保管费、白蚁防治、电缆线路标 安全措施费及文明施工费(Y 36,560 元,已包含在工程限价内); 为完成工程发生的有关费用; 材料归属: 1.5.1 本工程供电局提供清单上的材料; 1.5.2 甲方提供Y 1,398,535 元钢筋、混凝土及顶管管材的工程施工材料; 1.5.3 非上述约定材料由乙方负责。 分包合同价款 金额:大写:人民币伍佰壹拾万玖仟壹佰元整,小写:土5,109,100.00 元 工期 开工日期:本分包工程定于2011 年11月1日开工;志桩 1.3 1.4 1.5

分包合同模板8篇

分包合同模板8篇 分包合同篇1 合同编号: 建设工程施工分包 室外保温合同 施工总承包人 劳务分包人: 建设工程施工劳务分包合同书 施工总承包人: 以下简称甲方 单项工程分包人:以下简称乙方 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其它有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,签于我方(以下简称为建设单位)与工程承包人已经签订了施工总承包合同(以下简称总包合同),双方就土建主体结构及装修工程劳务合同分包事项协商达成一致,订立本合同。 一、工程名称: 二、工程地点: 三、工程内容:XX 楼室外保温(外墙110mm厚聚苯乙烯泡沫塑料板) 四、交工日期: 20xx年7月15日 五、承包内容:

5.1施工图纸范围内的外保温及装修涂料工程,包括外墙保温、聚苯防木椽、滴水条、滴水槽、窗边造型及聚苯线条、线脚等图纸上所标示的所有聚苯板装饰性线条的制作安装及其涂料。自开工到竣工验收结束的全部人工材料及辅助材料和小型机械(具)由乙方提供。(涂料工程只包人工费) 5.2该施工范围内的建筑垃圾及施工区的清理,垃圾运至甲方指定地点,并负责现场成品及半成品的保护至交到下道工序施工前的全部工作。 5.3该工程施工现场正常施工范围内的标准化工地建设用工。 5.4该单项工程所有复试检测费由乙方负责,涂料除外。 六、主要工作内容: 6.1外墙保温工程:提出保温材料用量的总计划,从外保温板的采购加工到安装、抗烈砂浆抹面、涂料墙及基层处理、涂料及现场材料的二次搬运等全部施工工程。 6.2涂料工程:包括墙面刮防水腻子、打磨清理所用的砂纸、所用小型机械(具)及手提工具等均由乙方自理;涂料、腻子粉、胶由甲方提供。 6.3脚手架工程:本工程结构施工采用双排48×3.0钢管外双排脚手架,现已搭设好,在施工过程中不得损坏和人为破坏,严禁工人私自乱拆外架上的任何设施,上架前必须由安全员先检查有无瞎眼跳探头板,施工用脚手板的层间翻板应自行根据需要翻板施工,高空作业必须正确佩戴安全防护用品,并必须保证安全防护用品符合安全标准要求。

施工总承包合同模板(标准版)

编号:FB-HT-05021 施工总承包合同(标准版) Template of general contract for construction 甲方:________________________ 乙方:________________________ 签订日期:_____年____月____日 编订:x原创设计

施工总承包合同(标准版) 发包方(以下简称甲方): 代表人: 承包方(以下简称乙方): 责任人: 依照合同法等相关法律、法规,本着友好、诚信的原则,甲方将______工程交由乙方承包,就相关事宜协商一致,达成如下协议: 一、工程项目 1、工程名称: 2、工程内容: 3、工程总量: 4、承包期限: 计划开工日期:______年______月______日,计划完工日期:______年______月_____日,总共_______

天。 5、工程价款: 6、支付方式: 7、工程质量: 二、双方职责 1、甲方职责 (1)负责施工前的准备工作,保证工程交接时符合施工条件。 (2)及时交付图纸,设计变更时要及时与乙方协商。 (3)对工程进行安全监督、检查。 (4)工程竣工时,及时组织人员进行验收。 (5)按时支付工程款,不得无故拖延。 2、乙方职责 (1)熟悉图纸与合同的所以内容。 (2)积极配合甲方在设计变更时的工作。 (3)安全生产,文明施工,酒后不得作业,不得穿拖鞋进场。

(4)工程完工时及时通知甲方验收。 (5)未经甲方同意,乙方不得将整个项目直接或变相转包给第三方。 三、安全条款 1、甲方负责监督乙方的生产作业,制定安全生产规范供乙方执行。 2、乙方确保施工环境的安全,一旦施工环境不符合施工条件,必须马上停工。 3、乙方必须严格执行国家、行业的安全规范,安全会议要经常开,安全知识要时时普及。 4、乙方必须规范每个工人的行为,不戴安全帽不得进场。 四、工程验收 1、乙方工程施工完成,已具备了竣工验收条件,必须提前______天按国家有关规定向监理单位和开发商提供完整的竣工图纸、相关资料及竣工验收报告等。 2、由于______工地是几个工程队同时在进行施工,所以工程量的测量以承包经营开始的红线范围、测量

专业分包施工合同(示范文本)

建设工程防水分包合同(示文本) 承包人:中建三局第设工程有限责任公司基础设施工程公司(以下简称甲方) 分包人:(以下简称乙方) 根据《中华人民国合同法》、《中华人民国建筑法》、《房屋建筑和市政基础设施工程施工分包管理办法》及其他有关法律,结合省、市及有关部门的相关规定和本工程具体情况,遵循平等、自愿、公平和诚实信用的原则,甲、乙双方就分包工程施工事项经过充分协商达成一致,特订立本合同。 第一条分包工程概况 1.1 工程名称: 1.2 工程地点: 1.3 分包围: 1.4 分包方式:单价包干,同时包工、包料、包机械、包质量、包工期、包安全文明施工 1.5 分包合同价(暂定):大写:人民币元(小写:元) 1.6 组成分包合同的文件及优先解释顺序为: 1.6.1 本合同及补充协议书; 1.6.2 中标通知书;(如有时) 1.6.3 甲方的招标文件及答疑;(如有时) 1.6.4 双方的议价记录 1.6.5 乙方的投标函及报价书; 1.6.6 本合同工程建设标准、图纸及有关技术文件。 本合同施工过程中甲方与乙方有关工程的洽商、变更等签字手续齐全的书面协议或文件也是本合同文件的组成部分。 第二条施工依据、材料名称及主要施工工艺 2.1施工依据:(业主下发的施工图纸编号或图集号) 2.2工程材料:(主要材料的名称、规格、系列名称、颜色、厚度等) 2.3主要施工工艺: 第三条工程工期

3.1 开工时间:(暂定)年月日,具体以甲方项目部书面通知的开工时间为准。 3.2 竣工时间:(暂定)年月日。 3.3 本合同工期总日历天数天。 3.4 在施工过程中,如遇下列情况则工期顺延: 3.4.1 由于人力不可抗拒的灾害; 3.4.2 甲方原因造成工期延误(连续七天以上),且甲方书面认可; 3.4.3 甲方书面认可的其它原因。 第四条工程质量要求 4.1 工程质量目标:必须达到合格,并符合GB 工程质量验收标准,满足规要求。 4.2 乙方必须严格按施工图及规要求施工,确保工程质量、安全、工期进度、文明施工、协调配合等方面达到甲方要求,本分包合同书签订前,乙方须向甲方提供人民币元(大写:元)作为履约保证金。本分包工程竣工验收后七日乙方向甲方提出书面申请,经甲方确认无误并按本合同文件有关规定执行后无息退还,若乙方不按要求交纳履约保证金,甲方不予办理工程结算,不予支付工程款,若乙方出现违约或欠付农民工工资的事实,甲方将从履约保证金中扣除违约金,若金额不足以抵扣,则从乙方的工程款中扣除。 4.3 乙方应认真按照甲方安排组织施工,随时接受甲方施工管理人员的监督、检查,建立部“三检制”为甲方验收积极创造条件,对甲方提出的质量问题及时整改。 第五条结算方式 5.1合同工作容: (详细说明合同单价包括了那些工作容、耗用材料、施工措施、技术措施、现场管理等) 5.2工程量计算: 按施工蓝图加设计变更计算工程量。根据省市建设工程造价管理部门颁布的工程量计算规定文件计算。 5.3 合同单价: 防水按元/M2包干(其中人工费为元/M2),不作任何调整。 金额单位:元(如果有几项单价,就用 此表)