搜档网
当前位置:搜档网 › bozhan_tif_ch07

bozhan_tif_ch07

bozhan_tif_ch07
bozhan_tif_ch07

Chapter 7 Process Choice and Layout Decisions in Manufacturing and Services TRUE/FALSE

1.No manufacturing process can be best at everything.

Answer: True

Reference: Introduction

Difficulty: Easy

Keywords: manufacturing, process

2. A product-based layout arranges resources sequentially according to the steps required to

make a product.

Answer: True

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: product, layout, product-based

3.Cycle time is the sum of all of the task times.

Answer: False

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: product, layout, cycle, time

AACSB: Analytic Skills

4. A job shop manufacturing process is better suited to make a variety of products than a

continuous flow process.

Answer: True

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: continuous, job shop, process

5. A batch process is less flexible than an assembly line and less efficient that a job shop.

Answer: False

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: batch, process, assembly line, job shop

6. A cellular layout is another name for a functional layout.

Answer: False

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: cellular, cell, functional, layout

7. A customer service function at an insurance firm that handles claims based on the first letter

of the customer’s last name is an example of applying group technology to a service

operation.

Answer: False

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: cellular, cell, group technology

AACSB: Reflective Thinking

8.The product-process matrix illustrates that low volume, one-of-a-kind products are ideally

suited to a job shop process.

Answer: True

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: product, process, layout, job shop

9.Make-to-stock products are probably produced using a production line.

Answer: True

Reference: Product Customization within the Supply Chain

Difficulty: Moderate

Keywords: make-to-stock, MTS, customization, production line

AACSB: Reflective Thinking

10.Products that use standard components, but the final configuration of those components is

customer-specific are called make-to-order products.

Answer: True

Reference: Product Customization within the Supply Chain

Difficulty: Easy

Keywords: make-to-order, MTO, customization

11.Activities that take place prior to the point of customization are called upstream activities.

Answer: True

Reference: Product Customization within the Supply Chain

Difficulty: Easy

Keywords: customization, upstream

12.According to the law of variability, converting from an assemble-to-order to a make-to-order

production process should increase productivity of the manufacturing processes.

Answer: False

Reference: Product Customization within the Supply Chain

Difficulty: Difficult

Keywords: assemble, make, order, variability, law of variability, productivity

AACSB: Reflective Thinking

13.In a service process, the greater the emphasis on intangible activities is the more critical is the

training and retention of skilled employees and the development and maintenance of the firm’s knowledge assets.

Answer: True

Reference: Service Processes

Difficulty: Moderate

Keywords: service, process, intangible

14.As the degree of service customization decreases, managers have more opportunity to focus

on cost and productivity.

Answer: True

Reference: Service Processes

Difficulty: Moderate

Keywords: service, process, customization

15.The back room refers to the part of the service process where the customer is not visible to

the other customers waiting for service.

Answer: False

Reference: Service Processes

Difficulty: Moderate

Keywords: service, processes, back, room, back room

16.The three dimensions of service positioning are the service package, the degree of

customization and the amount of customer contact.

Answer: True

Reference: Service Processes

Difficulty: Moderate

Keywords: service, process, package, customization, contact

17.Takt time is the upper limit on the elapsed time between completions of successive items on a

production line.

Answer: True

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: takt, cycle, time

AACSB: Analytic Skills

18.A manager deciding where 6 departments could be located in a six room office building has

over 500 possible arrangements.

Answer: True

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: functional, layout, location

AACSB: Analytic Skills

MULTIPLE CHOICE

19.A manufacturing process decision affects:

a.the type of workforce needed.

b.the type of equipment needed.

c.the type of products that can be made.

d.All of the above are correct.

Answer: d

Reference: Introduction

Difficulty: Easy

Keywords: manufacturing, process, decision, workforce, equipment, product

20.Highly automated batch processes that can reduce the cost of making similar groups of

products are:

a.functional layouts.

b.flexible manufacturing systems.

c.make-to-stock.

d.adjacent processes.

Answer: b

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: batch, processes, FMS, flexible, manufacturing

21.The time between completions of successive units on a production line is called:

a.cycle time.

b.takt time.

c.elapsed time.

d.work tim

e.

Answer: a

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: production line, cycle

22.An advantage of a production line process is:

a.the volume of output needed to justify the investment.

b.the degree of flexibility of the process.

c.the per unit cost of items produced on the line.

d.the range of output typically produced on such a process.

Answer: c

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: production line, cost, flexibility

23.The manufacturing process used to make a wide variety of highly customized products in

quantities as small as one is a:

a.production line.

b.continuous flow process.

c.job shop.

d.fixed position

Answer: c

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: production line, cost, flexibility

24.A sporting apparel manufacturer that produces t-shirts to commemorate significant athletic

achievements for proud students and alumni probably uses:

a. a fixed position layout.

b.batch manufacturing.

c. a continuous flow process.

d. a production lin

e.

Answer: b

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: production line, cost, flexibility

AACSB: Reflective Thinking

25.Products that are customized only at the very end of the manufacturing process are known as:

a.make-to-stock.

b.assemble-to-order.

c.make-to-order.

d.engineer-to-order.

Answer: b

Reference: Product Customization within the Supply Chain

Difficulty: Easy

Keywords: assemble-to-order, order, finish, ATO

26.Products that use standard components but the final configuration of those components is

customer-specific are known as:

a.make-to-stock.

b.assemble-to-order.

c.make-to-order.

d.engineer-to-order.

Answer: c

Reference: Product Customization within the Supply Chain

Difficulty: Easy

Keywords: make-to-order, order, make, MTO

27.Assemble-to-order occurs upstream from:

a.design.

b.material sourcing.

c.fabrication.

d.finishing.

Answer: d

Reference: Product Customization within the Supply Chain

Difficulty: Moderate

Keywords: assemble-to-order, order, assemble, ATO, finishing

28.The greater the emphasis on intangible activities, the more management’s attention will be

directed to:

a.buildings and property.

b.training employees.

c.truck fleets.

d.material costs.

Answer: b

Reference: Service Processes

Difficulty: Moderate

Keywords: intangible, service

29.The point where the customer interfaces directly with the service organization is:

a.the front room.

b.the back room.

c.onstage.

d.the floor.

Answer: a

Reference: Service Processes

Difficulty: Moderate

Keywords: front, room, customer, service

30.A legal service in a corporate acquisition probably scores:

a.low on customization and high on physical activities.

b.high on customer contact and low on intangible activities.

c.high on customization and high on intangible activities.

d.low on customer contact and low on intangible activities.

Answer: c

Reference: Service Processes

Difficulty: Moderate

Keywords: service, process, positioning, customization, intangible

AACSB: Reflective Thinking

31.Champion Cooling has just signed a contract to assemble window air conditioners for another

company. The list of tasks, including time requirements and immediate predecessors, follows.

Initially, the plan was to make 300 units in an eight hour day but as the summer months

approach, Champion Cooling finds themselves far behind in total production. They wish to reconfigure their production line in order to produce maximum output. What should their

b. 6

c.7

d.10

Answer: d

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: line balance, takt, time

AACSB: Analytic Skills

32.The process design team at a manufacturer has broken an assembly process into eight basic

steps, each with a required time, and predecessor as shown in the table. They work a 7 hour

b.65 seconds

c.52 seconds

d.25 seconds

Answer: a

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: line, balance, takt, time

AACSB: Analytic Skills

33.The process design team at a manufacturer has broken an assembly process into eight basic

steps, each with a required time, and predecessor as shown in the table. There are 8

productive hours available in a day and the manufacturer wishes to produce 400 units. What

b.three stations

c.four stations

d.five stations

Answer: d

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: line, balance, station

AACSB: Analytic Skills

34.The process design team at a manufacturer has broken an assembly process into eight basic

steps, each with a required time, and predecessor as shown in the table. There are 7.5

productive hours available in a day and the manufacturer wishes to produce 400 units.

Balance the line by assigning tasks to workstations to fill up as much takt time as possible.

Break ties by assigning the longest task first. What tasks should be assigned at the third

b. D

c.C, E, and G

d. F

Answer: a

Reference: Layout Decision Models

Difficulty: Difficult

Keywords: line, balance, station

AACSB: Analytic Skills

35.The table depicts an assembly line that has been balanced with a takt time of 2 minutes. What

b.10%

c.15%

d.Cannot be determined from the information provided.

Answer: b

Reference: Layout Decision Models

Difficulty: Moderate

Keywords: line, balance, takt, efficiency delay

AACSB: Analytic Skills

36.These three tables show the floor layout of 5 departments in an office building, the average

number of daily trips between each pair of offices, and the distance between each pair of

b.$2300.00

c.$3037.50

d.$4785.50

Answer: c

Reference: Layout Decision Models

Difficulty: Difficult

Keywords: functional, layout, distance

AACSB: Analytic Skills

FILL IN THE BLANK

37.A(n) __________ is a highly automated batch process that can reduce the cost of making

groups of similar products.

Answer: flexible manufacturing system, FMS

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: flexible, manufacturing, system, FMS

38.__________ gets its name from the fact that items are moved through the different

manufacturing steps in groups.

Answer: Batch manufacturing

Reference: Manufacturing Processes

Difficulty: Easy

Keywords: batch, manufacturing, process

39.A cellular layout is essentially the opposite of a(n) __________ layout.

Answer: functional

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: cellular, layout, functional

40.The product process matrix uses a scale of __________ and __________.

Answer: volume, standardization

Reference: Manufacturing Processes

Difficulty: Difficult

Keywords: product, process, matrix

41.__________ products involve no customization but __________ products are completely

customized.

Answer: Make-to-stock, engineer-to-order

Reference: Product Customization within the Supply Chain

Difficulty: Moderate

Keywords: engineer, make, order, stock

42.__________ are products that are customized only at the very end of the manufacturing

process.

Answer: Assemble-to-order

Reference: Product Customization within the Supply Chain

Difficulty: Easy

Keywords: assemble-to-order, ATO

43.According to the law of variability, the __________ the random variability either demanded

of the process or inherent in the process itself or in the items processed, the __________ productive the process is.

Answer: greater, less; lower, more

Reference: Product Customization within the Supply Chain

Difficulty: Moderate

Keywords: law, variability, productivity

44.The __________ includes all value-added physical and intangible activities that a service

organization provides to the customer.

Answer: service package

Reference: Service Processes

Difficulty: Easy

Keywords: service package, intangible, value-added

45.As the degree of customer contact decreases, more of the service package is provided by the

__________.

Answer: back room

Reference: Service Processes

Difficulty: Moderate

Keywords: service, back room, back, room

46.The maximum allowable cycle time for a production line is the __________.

Answer: takt time

Reference: Layout Decision Models

Difficulty: Easy

Keywords: layout, cycle, takt, time

ESSAY

47.Why are process decisions important?

Answer: Process decisions are important because they tend to be expensive and far-

reaching. A process choice dictates the type and size of the workforce and the type of

equipment that is needed. Different processes have different strengths and weaknesses.

Reference: Introduction

Difficulty: Easy

Keywords: process, decision

48. Sketch the product-process matrix and discuss the placement of each process choice.

Answer: The product process matrix relates output volume and degree of customization and shows which process technologies have the greatest chance for success in each combination of volume and customization. A job shop is best suited to make low volumes of highly customized (low standardization) products and a production line is best for generating large volumes of highly standardized products. Positions off of the diagonal represent limited chances of company survival and are generally thought to

Reference: Manufacturing Processes Difficulty: Difficult

Keywords: process, product, matrix

P

r

o

c e s s C h o i c

e

49.What is a cellular layout and what are its advantages?

Answer: A cellular layout is a type of layout typically used in group technology settings;

resources are physically arranged according to the dominant flow of activities for the

product family. Group technology is achieved when clusters of machines and or

personnel are dedicated to the production of products (or service of customers) that are

similar. A cellular layout reduces transportation and congestion on the production floor.

Reference: Manufacturing Processes

Difficulty: Moderate

Keywords: cell, cellular, group technology

50.What are the four levels of customization and at what place does each occur in the supply

chain?

Answer: The four levels ranked from least to greatest customization are make-to-stock,

assemble-to-order, make-to-order, and engineer-to-order. Make-to-stock products have

no customization and are typically produced in large enough volumes to warrant keeping

a finished goods inventory. Assemble-to-order products are customized at the very end of

the manufacturing process. Make-to-order products use standard components, but the

final configuration of those components is customer specific. Engineer-to-order products are designed and produced from the start to meet customer requirements. Engineer-to-

order products are customized upstream from design. Make-to-order products are

customized downstream from material sourcing and upstream from fabrication.

Assemble-to-order products are customized downstream from fabrication and upstream

from assembly. The text indicates that make-to-stock products are customized

downstream from assembly and upstream from distribution, although this customization may be only in the order quantity.

Reference: Product Customization within the Supply Chain

Difficulty: Moderate

Keywords: product, customization, make, engineer, assemble, stock, order

AACSB: Reflective Thinking

51.Define the term service package and describe management’s focus for each activity.

Answer: A service package includes all the value-added physical and intangible

activities that a service organization provides to the customer. For some service

operations, the primary sources of value are physical (or tangible) activities. In this case, manageme nt’s attention must be directed towards capital expenditures, material costs and other tangible assets. For some service operations, the service package consists primarily of intangible activities. If this is the case, management should focus on training and

retention of skilled employees.

Reference: Service Processes

Difficulty: Moderate

Keywords: service package, physical, intangible

52. A manufacturer needs to produce 300 coffee pots per 8 hour day. The discrete tasks required

to produce a coffee pot have been identified, timed in seconds, and ordered as indicated in the table. Sketch the precedence diagram and then assign tasks to workstations on the production line to achieve the required level of output. Break ties by assigning the longest task first.

The takt time for 300 units in 8 hours is

8 hr/day 60 min/hr 60 sec/min

takt time 96 sec/unit 300 units

??=

=

100%100%100%75 100%100%84.375%

480IT

Efficiency delay PI TI Efficiency delay ?

?=-=-?

? ??

???

=-= ???

∑ Reference: Layout Decision Models

Difficulty: Difficult

Keywords: production line, balance, takt, cycle AACSB: Analytic Skills

53. What is the optimal location for these departments in the floor plan depicted if the

transportation cost is $2 per foot and the departments have a daily number of trips between

Answer:

Multiple answers are possible; for example, a mirror image of DBEAC yields an identical {}{}{}{} $22020'4010'6030'8010' 1030'3010'5010' 040'1520' 520' $9800

Total C ost Trips D istance

$2/ft departm ent A $2/ft departm ent B $2/ft departm ent C $2/ft departm ent D =

??=?+?+?+?+?+?+?+?+?+?=

Reference: Layout Decision Models

Difficulty: Difficult

Keywords: process, layout, department, assignment AACSB: Analytic Skills

相关主题